If you are installing solar panels at your business, the grid interconnection process with CFE (Mexico's federal electricity utility) is the legal procedure that allows you to connect your system to the national power grid and take advantage of the applicable metering scheme. Although it sounds complex, with the right guidance it is an orderly and predictable process.
What is grid interconnection?
It is the contract you sign with CFE so your solar system can operate connected to the grid. Thanks to it, the energy your business does not consume at the moment can be credited, and your meter records both what you draw from the grid and what you feed into it.
The process, step by step
- 1. Study and design: the system is sized based on your historical consumption and the capacity to be interconnected is defined.
- 2. Interconnection application: the project's technical documentation and the property information are submitted to CFE.
- 3. Review and approval: CFE verifies that the system complies with regulations and with the grid conditions in your area.
- 4. Installation and meter replacement: the equipment is installed and CFE installs a bidirectional meter.
- 5. Contract signing and energization: the interconnection contract is formalized and the system goes into operation.
How long does it take?
The complete process, from quote to energization, usually takes between 30 and 60 days, depending on the system's capacity and CFE's timelines in your region.
Documents typically required
- Identification of the service holder and the property.
- Recent CFE bills.
- Technical specifications for panels and inverters.
- Electrical diagram of the system.